HS2 remains on budget… but which budget?

HS2 remains on budget… but which budget?


Chalfont St Peter vent shaft for the Chiltern tunnels

The current budget for HS2 Phase One (London-Birmingham) stands at £44.6bn. Of this, £14.9bn has been spent, with an additional £800m for land and property provisions. £12.7bn has been contracted but not yet actually spent.

That £44.6bn budget figure is not what the government orHS2 Ltd expects it to cost. It should ‘only’ cost £34.7bn – including systems and trains as well as construction. However £5.6bn has been added for contingencies to give HS2 Ltd a target cost of £40.3bn.

To this £40.3bn target cost the government has added another £4.3bn contingencies of its own, to arrive at a ‘budget’ of £44.6bn.

So were HS2 Phase One to come in at £42.0bn, the government (and the client organisations) would be able to crow that the project had come in £2.6bn under budget – even though it would have actually cost £7.3bn more than it should have.

Those £9.9bn contingencies are there for a reason.

HS2 Ltd has so far drawn £1.3bn of its £5.6bn delegated contingency, including £500m in the past six months, meaning £4.3bn remains.

HS2 Ltd is reporting £1.7bn of “potential future cost pressures that are currently presenting across the programme”. These include an estimate of £800m for potential additional main works civils costs stemming from additional design costs and slower than expected progress in some areas. That figure has risen from £200m six months ago.

There is also a “pressure” of £400m on the cost estimate for the HS2 Euston station and £200m against HS2 Ltd’s budget for changes to Network Rail infrastructure at Euston and Old Oak Common that are required to facilitate the new HS2 stations.

On Covid-19 costs, HS2 Ltd’s assessment of the likely financial impact of the pandemic on delivering Phase One is estimated within the range of £400m to £700m.

Ongoing protester activity, including the removal of camps and protest-related delays to the programme, has cost nearly £122m so far.

The minister’s full report can be read at www.gov.uk

Got a story? Email [email protected]



Source link


Customer Reviews

Nugen Properties

Customer Reviews

Dan Morten 18/01/22

Google
Easy to work with, Jordan and the team were professional and were easy to communicate with.
Would highly recommend.

Di Hayes 20/08/22

Google
NuGen Properties built an extension to the rear of my property, replacing the old conservatory. I am so pleased I chose this company. From the initial quotation, through the build and after they were professional, polite & well mannered. They kept the site tidy throughout the build and kept me informed of each stage as it happened. The work was finished to a good standard and I have had nothing but compliments on their work. I am already planning for them to come back and do some more work for me in a few months. I would 100% recommend them.

Bradley Eyles 20/06/23

Google
Nugen were fantastic throughout the works they carried out on my property, Jordan provided constant updates and ensure any questions I had were always answered. All works were completed in a timely fashion, on budget and exceptional customer service. Highly recommend!

Sonny Carter-heyward 29/02/22

Google
Brilliant service, renovated my house to make a dream a reality. Thanks guys

sitemanager 22/01/23

Google
Great firm to communicate with fast and good quality work.