Inadequate prep blamed for platform collapse


The platform fell during dismantling of the Brent Bravo

Errors by Able UK Limited caused an employee to suffer life threatening injuries after falling 15 metres when a platform, on which he was working, collapsed.

Teesside Magistrates Court heard how that on 31st July 2019, the worker was involved in the dismantling of the Brent Bravo, a former North Sea oil and gas platform.

Able UK was contracted to dismantle four platforms from the Brent North Sea oil and gas field. The incident occurred during the removal of a module located on the northwest corner of the Brent Bravo Platform. In planning for the removal of the module, it was noted that there were three platforms on the cellar deck of the structure that would need to be moved to allow the module to fall safely.

It was not recognised by the planning team that one of the platforms did not form part of the main structure and was attached to the platform using bolts that had corroded over time.  This affected the structural integrity of the platform and the methodology required to remove it safely.  During the cutting of bracing beams, the platform unexpectedly collapsed causing one of the employees to fall 15 metres.

An investigation by the Health & Safety Executive (HSE) into the incident found that Able UK failed to carry out a full structural appraisal of the platform prior to demolition. This would have informed the risk assessment and method statement being used by the cutting crew at the time of the incident to ensure that the work could have been carried out safely.

Able UK Limited, of Billingham Reach Industrial Estate in Cleveland, pleaded guilty to breaching Regulation 2(1) of The Health and Safety at Work act 1974. It was fined £200,000 with £20,991.24 costs by Teesside magistrates.

HSE inspector Richard Littlefair said after the hearing: “When undertaking demolition work where structures are being left in a pre-weakened state, it is essential for those in control of the work to take appropriate measures to ensure the safety of all those involved with the work.  This includes ensuring that consideration is given to the stability of structures before and during demolition work, as well as ensuring that control measures are in place to mitigate other associated health and safety risks such as work at height.”

Got a story? Email [email protected]



Source link


Customer Reviews

Nugen Properties

Customer Reviews

Dan Morten 18/01/22

Google
Easy to work with, Jordan and the team were professional and were easy to communicate with.
Would highly recommend.

Di Hayes 20/08/22

Google
NuGen Properties built an extension to the rear of my property, replacing the old conservatory. I am so pleased I chose this company. From the initial quotation, through the build and after they were professional, polite & well mannered. They kept the site tidy throughout the build and kept me informed of each stage as it happened. The work was finished to a good standard and I have had nothing but compliments on their work. I am already planning for them to come back and do some more work for me in a few months. I would 100% recommend them.

Bradley Eyles 20/06/23

Google
Nugen were fantastic throughout the works they carried out on my property, Jordan provided constant updates and ensure any questions I had were always answered. All works were completed in a timely fashion, on budget and exceptional customer service. Highly recommend!

Sonny Carter-heyward 29/02/22

Google
Brilliant service, renovated my house to make a dream a reality. Thanks guys

sitemanager 22/01/23

Google
Great firm to communicate with fast and good quality work.