Newham wins landmark cladding removal case

Newham wins landmark cladding removal case


The Lumiere building [from Google Streetview]

City of London Magistrates Court this week ruled against Chaplair Ltd after it failed to meet a deadline to remove dangerous cladding from its Lumiere building at 544 Romford Road, London E7. 

Newham Council pursued legal action using its powers under the Housing Act 2004 after Chaplair failed to remove dangerous cladding on the Lumiere building by the 31st March 2021 deadline imposed in an improvement notice issued by the council in September 2020. 

Work eventually began in May 2021, with dangerous cladding removed by February 2022. Through its legal action, the council successfully argued that there was no reasonable excuse for the delay.

Mayor of Newham Rokhsana Fiaz said: “Through our Newham Cladding Action campaign to protect the rights of residents in our borough, we have zero tolerance for owners of buildings delaying essential life-saving fire safety work. Failing to remove dangerous cladding as quickly as possible places lives at risk and, where necessary, we will act with full force using the powers we have to protect our residents.

“Six years after the Grenfell Tower disaster, today’s decision by the court symbolises a landmark ruling in our fight to raise standards and hold building owners to account in Newham. It will also help authorities across the country to safeguard the interests of their residents using the powers available under vital housing legislation.

“This monumental ruling sends a clear warning to all building owners operating in Newham that they must act swiftly in the interest of our residents’ safety first and always, otherwise we will take decisive action against you.”

In his ruling, deputy chief magistrate Tan Ikram wrote: “The prosecution have satisfied me so that I am sure that a valid improvement notice was served and the defendant company did not carry out the required remedial works relating to the external facades within the required period.  The defendants have failed to satisfy me that they have reasonable excuse in failing to comply with the improvement notice. I therefore find Chaplair Ltd guilty of the offence.”

The case will return for sentencing on Tuesday 31st October 2023 at Westminster Magistrates Court.

Got a story? Email [email protected]



Source link


Customer Reviews

Nugen Properties

Customer Reviews

Dan Morten 18/01/22

Google
Easy to work with, Jordan and the team were professional and were easy to communicate with.
Would highly recommend.

Di Hayes 20/08/22

Google
NuGen Properties built an extension to the rear of my property, replacing the old conservatory. I am so pleased I chose this company. From the initial quotation, through the build and after they were professional, polite & well mannered. They kept the site tidy throughout the build and kept me informed of each stage as it happened. The work was finished to a good standard and I have had nothing but compliments on their work. I am already planning for them to come back and do some more work for me in a few months. I would 100% recommend them.

Bradley Eyles 20/06/23

Google
Nugen were fantastic throughout the works they carried out on my property, Jordan provided constant updates and ensure any questions I had were always answered. All works were completed in a timely fashion, on budget and exceptional customer service. Highly recommend!

Sonny Carter-heyward 29/02/22

Google
Brilliant service, renovated my house to make a dream a reality. Thanks guys

sitemanager 22/01/23

Google
Great firm to communicate with fast and good quality work.